DecisionDepot
California legal research

Texas Utilities Code

§ 39.166 — RELIABILITY PLAN FOR REGIONS WITH RAPID ELECTRICAL LOAD GROWTH

UT § 39.166Title 2. PUBLIC UTILITY REGULATORY ACT · Part B. ELECTRIC UTILITIES · Ch. 39. RESTRUCTURING OF ELECTRIC UTILITY INDUSTRY · Art. D. MARKET STRUCTURE

Statute text

View on source
(a)The commission shall direct the independent organization certified under Section 39.151 for the ERCOT power region to:
(1)identify each region in which transmission capacity is insufficient to meet the region's existing and forecasted electrical load, as reasonably determined by the certificated transmission service provider; and
(2)develop a reliability plan to serve existing and forecasted electrical load in the identified region.
(b)The commission shall develop a plan to implement each reliability plan adopted under Subsection (a) to ensure timely development and approval of necessary transmission service improvements.

Legislative history

Added by Acts 2023, 88th Leg., R.S., Ch. 892 (H.B. 5066), Sec. 3, eff. June 13, 2023.