View on source(a)This section applies only to an electric utility that operates solely outside of ERCOT.
(b)In establishing the base rates of the electric utility under this subchapter or Subchapter D, the regulatory authority shall determine the utility's revenue requirement based on, at the election of the utility:
(1)information submitted for a test year; or
(2)information submitted for a test year, updated to include information that reflects the most current actual or estimated information regarding increases and decreases in the utility's cost of service, including expenses, capital investment, cost of capital, and sales.
(c)An electric utility that elects to provide updated information under Subsection (b)(2) must provide the information for a period ending not later than the 30th day before the date the applicable rate proceeding is filed.
(d)An electric utility that includes estimated information in the initial filing of a proceeding shall supplement the filing with actual information not later than the 45th day after the date the initial filing was made. The regulatory authority shall extend the deadline for concluding the rate proceeding for a period of time equal to the period between the date the initial filing of the proceeding was made and the date of the supplemental filing, except that the extension period may not exceed 45 days.
…