Texas Property Code
§ 53.234 — TIME FOR NOTICE
PR § 53.234Title 5. EXEMPT PROPERTY AND LIENS · Part B. LIENS · Ch. 53. MECHANIC'S, CONTRACTOR'S, OR MATERIALMAN'S LIEN · Art. J. LIEN ON MONEY DUE PUBLIC WORKS CONTRACTOR
Statute text
View on sourceThe lien claimant must give notice not later than the 15th day of the second month following the month in which the labor was performed or the material furnished. Acts 1983, 68th Leg., p. 3555, ch. 576, Sec. 1, eff. Jan. 1, 1984. Amended by Acts 1989, 71st Leg., ch. 1138, Sec. 36, eff. Sept. 1, 1989. Amended by:
Legislative history
Acts 2009, 81st Leg., R.S., Ch. 1304 (H.B. 2515), Sec. 3, eff. September 1, 2009.