Texas Property Code
§ 53.159 — OBLIGATION TO FURNISH INFORMATION
PR § 53.159Title 5. EXEMPT PROPERTY AND LIENS · Part B. LIENS · Ch. 53. MECHANIC'S, CONTRACTOR'S, OR MATERIALMAN'S LIEN · Art. G. RELEASE AND FORECLOSURE; ACTION ON CLAIM
Statute text
View on source(a)An owner, on written request, shall furnish the following information within a reasonable time, but not later than the 10th day after the date the request is received, to any person furnishing labor or materials for the project:
(1)a description of the real property being improved legally sufficient to identify it;
(2)whether there is a surety bond and if so, the name and last known address of the surety and a copy of the bond;
(3)whether there are any prior recorded liens or security interests on the real property being improved and if so, the name and address of the person having the lien or security interest; and
(4)the date on which the original contract for the project was executed.
(b)An original contractor, on written request by a person who furnished work under the original contract, shall furnish to the person the following information within a reasonable time, but not later than the 10th day after the date the request is received:
…
Legislative history
Acts 2011, 82nd Leg., R.S., Ch. 499 (H.B. 1390), Sec. 7, eff. September 1, 2011.