§ 53.056 — DERIVATIVE CLAIMANT: NOTICE TO OWNER AND ORIGINAL CONTRACTOR
PR § 53.056Title 5. EXEMPT PROPERTY AND LIENS · Part B. LIENS · Ch. 53. MECHANIC'S, CONTRACTOR'S, OR MATERIALMAN'S LIEN · Art. C. PROCEDURE FOR PERFECTING LIEN
Statute text
View on source(a)Except as provided by Section 53.057, a claimant other than an original contractor must give the notice prescribed by Subsections (a-1) and (a-2) for the lien to be valid. (a-1) For all unpaid labor or materials provided, the claimant must send a notice of claim for unpaid labor or materials to the owner or reputed owner and the original contractor. The notice must be sent:
(1)for projects other than residential construction projects, not later than the 15th day of the third month after the month during which:
(A)the labor or materials were provided; or
(B)the undelivered specially fabricated materials would normally have been delivered; or
(2)for residential construction projects, not later than the 15th day of the second month after the month during which:
(A)the labor or materials were provided; or
…
Legislative history