§ 53.054 — CONTENTS OF AFFIDAVIT

PR § 53.054Title 5. EXEMPT PROPERTY AND LIENS · Part B. LIENS · Ch. 53. MECHANIC'S, CONTRACTOR'S, OR MATERIALMAN'S LIEN · Art. C. PROCEDURE FOR PERFECTING LIEN

Statute text

View on source
(a)The affidavit must be signed by the person claiming the lien or by another person on the claimant's behalf and must contain substantially:
(1)a sworn statement of the amount of the claim;
(2)the name and last known address of the owner or reputed owner;
(3)a general statement of the kind of work done and materials furnished by the claimant and, for a claimant other than an original contractor, a statement of each month in which the work was done and materials furnished for which payment is requested;
(4)the name and last known address of the person by whom the claimant was employed or to whom the claimant furnished the materials or labor;
(5)the name and last known address of the original contractor;

Legislative history

Acts 1983, 68th Leg., p. 3540, ch. 576, Sec. 1, eff. Jan. 1, 1984. Amended by Acts 1989, 71st Leg., ch. 1138, Sec. 6, eff. Sept. 1, 1989; Acts 1997, 75th Leg., ch. 526, Sec. 6, eff. Sept. 1, 1997.