§ 214.904 — TIME FOR ISSUANCE OF MUNICIPAL BUILDING PERMIT
LG § 214.904Title 7. REGULATION OF LAND USE, STRUCTURES, BUSINESSES, AND RELATED ACTIVITIES · Part A. MUNICIPAL REGULATORY AUTHORITY · Ch. 214. MUNICIPAL REGULATION OF HOUSING AND OTHER STRUCTURES · Art. Z. MISCELLANEOUS POWERS AND DUTIES
Statute text
View on source(a)This section applies only to a permit required by a municipality to erect or improve a building or other structure in the municipality or its extraterritorial jurisdiction.
(b)Not later than the 45th day after the date an application for a permit is submitted, the municipality must:
(1)grant or deny the permit;
(2)provide written notice to the applicant stating the reasons why the municipality has been unable to grant or deny the permit application; or
(3)reach a written agreement with the applicant providing for a deadline for granting or denying the permit.
(c)For a permit application for which notice is provided under Subsection (b)(2), the municipality must grant or deny the permit not later than the 30th day after the date the notice is received.
…
Legislative history
Added by Acts 2005, 79th Leg., Ch. 917 (H.B. 265), Sec. 1, eff. September 1, 2005.