(a)In this section, "energy savings performance contract" has the meaning assigned by Section 302.001, Local Government Code.
(b)The governing board of an institution of higher education may enter into an energy savings performance contract in accordance with this section.
(c)Each energy or water conservation measure must comply with current local, state, and federal construction, plumbing, and environmental codes and regulations. Notwithstanding Subsection (a), an energy savings performance contract may not include improvements or equipment that allow or cause water from any condensing, cooling, or industrial process or any system of nonpotable usage over which the public water supply system officials do not have sanitary control, to be returned to the potable water supply.
(d)The board may enter into energy savings performance contracts only with entities that are experienced in the design, implementation, and installation of the energy or water conservation measures addressed by the contract.
(e)Before entering into an energy savings performance contract, the board shall require the provider of the energy or water conservation measures to file with the board a payment and performance bond in accordance with Chapter 2253, Government Code. The board may also require a separate bond to cover the value of the guaranteed savings on the contract.
(f)The board may enter into an energy savings performance contract for a period of more than one year only if the board finds that the amount the institution would spend on the energy or water conservation measures will not exceed the amount to be saved in energy, water, wastewater, and operating costs over 20 years from the date of installation. If the term of the contract exceeds one year, the institution's contractual obligation in any year during the term of the contract beginning after the final date of installation may not exceed the total energy, water, wastewater, and operating cost savings, including electrical, gas, water, wastewater, or other utility cost savings and operating cost savings resulting from the measures, as determined by the board in this subsection, divided by the number of years in the contract term beginning after the final date of installation. The board shall consider all costs of the energy or water conservation measures, including costs of design, engineering, installation, maintenance, repairs, and debt service.

Legislative history

Acts 2007, 80th Leg., R.S., Ch. 527 (S.B. 831), Sec. 2, eff. June 16, 2007. Acts 2011, 82nd Leg., R.S., Ch. 982 (H.B. 1728), Sec. 3, eff. September 1, 2011. Acts 2011, 82nd Leg., R.S., Ch. 1129 (H.B. 628), Sec. 3.02, eff. September 1, 2011. Acts 2013, 83rd Leg., R.S., Ch. 161 (S.B. 1093), Sec. 22.002(7), eff. September 1, 2013. Acts 2013, 83rd Leg., R.S., Ch. 537 (S.B. 533), Sec. 1, eff. June 14, 2013. Acts 2017, 85th Leg., R.S., Ch. 258 (H.B. 1571), Sec. 2, eff. May 29, 2017.