View on leginfo.ca.gov(a)The commission shall determine the criteria for timely service for electric customers to be energized. The criteria shall include, but are not limited to, all of the following:
(1)Categories of timely electric service through energization, including, but not limited to, both of the following:
(A)The timely start of service, and timely fulfillment of requests, for energization, including new service connections and increased load from existing service connections after a customer has submitted a request for new or increased electrical load.
…
Legislative history
Added by Stats. 2023, Ch. 317, Sec. 1. (AB 50) Effective January 1, 2024.