California Public Utilities Code
§ 712.1
PUC § 712.1 Effective Jul 10, 2023Div. 1 · Part 1 · Ch. 4 · Art. 1
Statute text
View on leginfo.ca.gov(a)The Legislature finds and declares that in commission Decision 88-12-083 (December 19, 1988) Re Pacific Gas and Electric Company (30 CPUC.2d 189), the commission created the Independent Safety Committee for Diablo Canyon to make recommendations appropriate to enhance the safety of the operation of the Diablo Canyon powerplant.
(b)The Independent Safety Committee for Diablo Canyon shall continue to have the rights established pursuant to commission Decision 88-12-083, as amended by Decisions 07-01-028 and 21-09-003, to conduct annual examinations of the Diablo Canyon powerplant and make additional site visits. The committee shall cease operations no sooner than when the Diablo Canyon powerplant has ceased operations and all spent nuclear fuel has been moved to dry storage at the Diablo Canyon Independent Spent Fuel Storage Installation.
(c)The Independent Safety Committee for Diablo Canyon shall be composed of three experts, one each shall be appointed by the Governor, the Attorney General, and the Chair of the Energy Commission, from a list of candidates nominated by the President of the commission that shall include not more than three qualified candidates as alternatives to the reappointment of the appointing authority’s designated committee member whose term is expiring, and which shall also include the incumbent committee member if the member consents to being an additional candidate. The incumbent as of August 1, 2022, may continue to serve their current term until it expires.
…
Legislative history
Amended by Stats. 2023, Ch. 53, Sec. 9. (SB 124) Effective July 10, 2023.