View on leginfo.ca.gov(a)Notwithstanding paragraph (1) of subdivision (b) and paragraph (2) of subdivision (j) of Section 399.20, a conduit hydroelectric facility with an effective capacity of up to four megawatts that otherwise meets the requirements of Section 399.20 shall be eligible for the standard contract or tariff established pursuant to subdivision (c) of Section 399.20 if the electric generation facility meets all the following additional requirements:
(1)It was operational as of January 1, 1990.
(2)It delivers no more than three megawatts to the grid at any time.
…
Legislative history
Added by Stats. 2016, Ch. 665, Sec. 1. (AB 1979) Effective January 1, 2017.