California Public Utilities Code
§ 1005.1
PUC § 1005.1 Effective Dec 10, 2011Div. 1 · Part 1 · Ch. 5 · Art. 1
Statute text
View on leginfo.ca.gov(a)The commission shall issue a decision on an application for a certificate within 18 months of the date of filing of the completed application, when all of the following are true:
(1)The application is for a certificate for building or upgrading an electrical transmission line that the commission finds necessary to provide transmission to load centers for electricity generated in a high priority renewable energy zone or is reasonably necessary to facilitate achievement of the renewables portfolio standard established in Article 16 (commencing with Section 399.11) of Chapter 2.3.
(2)The commission has considered all of the following:
…
Legislative history
Added by Stats. 2011, 1st Ex. Sess., Ch. 1, Sec. 33. (SB 2 1x) Effective December 10, 2011.