View on leginfo.ca.govIn a proceeding evaluating the issuance of a certificate of public convenience and necessity for a proposed transmission project, the commission shall establish a rebuttable presumption with regard to need for the proposed transmission project in favor of an Independent System Operator governing board-approved need evaluation if all of the following are satisfied:
(a)The Independent System Operator governing board has made explicit findings regarding the need for the proposed transmission project and has determined that the proposed project is the most cost-effective transmission solution.
(b)The Independent System Operator is a party to the proceeding.
…
Legislative history
Added by Stats. 2023, Ch. 367, Sec. 10. (AB 1373) Effective October 7, 2023.