(a)Except as provided in this section, a person shall not conduct surface mining operations unless a permit is obtained from, a reclamation plan has been submitted to and approved by, and financial assurances for reclamation have been approved by the lead agency for the operation pursuant to this article.
(b)A person with an existing surface mining operation who has vested rights pursuant to Section 2776 and who does not have an approved reclamation plan shall submit a reclamation plan to the lead agency not later than March 31, 1988. If a reclamation plan application is not on file by March 31, 1988, the continuation of the surface mining operation is prohibited until a reclamation plan is submitted to the lead agency. For the purposes of this subdivision, a reclamation plan existing prior to January 1, 2017, may consist of all or the appropriate sections of any plans or written agreements previously approved by the lead agency or another agency, together with any additional documents needed to substantially meet the requirements of Sections 2772 and 2773 and the lead agency surface mining ordinance adopted pursuant to subdivision (a) of Section 2774, provided that all documents, which together were proposed to serve as the reclamation plan, are submitted for approval to the lead agency in accordance with this chapter.
(c)[Reserved]

Legislative history

Amended by Stats. 2018, Ch. 349, Sec. 2. (AB 3257) Effective January 1, 2019.

Source: California Public Resources Code § 2770 from the California Legislative Information (public record). DecisionDepot is for informational use only and is not legal advice — verify against the official source before relying on this text.