California Public Resources Code
§ 25540.6
PRC § 25540.6 Effective Jan 1, 2000Div. 15 · Ch. 6
Statute text
View on leginfo.ca.gov(a)Notwithstanding any other provision of law, no notice of intention is required, and the commission shall issue its final decision on the application, as specified in Section 25523, within 12 months after the filing of the application for certification of the powerplant and related facility or facilities, or at any later time as is mutually agreed by the commission and the applicant, for any of the following:
(1)A thermal powerplant which will employ cogeneration technology, a thermal powerplant that will employ natural gas-fired technology, or a solar thermal powerplant.
(2)A modification of an existing facility.
…
Legislative history
Amended by Stats. 1999, Ch. 581, Sec. 11. Effective January 1, 2000.