View on leginfo.ca.gov(a)(1) If an environmental impact report was certified for a planning level decision of a city or county, the application of this division to the approval of an infill project shall be limited to the effects on the environment that (A) are specific to the project or to the project site and were not addressed as significant effects in the prior environmental impact report or (B) substantial new information shows the effects will be more significant than described in the prior environmental impact report. A lead agency’s determination pursuant to this section shall be supported by substantial evidence.
(2)An effect of a project upon the environment shall not be considered a specific effect of the project or a significant effect that was not considered significant in a prior environmental impact report, or an effect that is more significant than was described in the prior environmental impact report if uniformly applicable development policies or standards adopted by the city, county, or the lead agency, would apply to the project and the lead agency makes a finding, based upon substantial evidence, that the development policies or standards will substantially mitigate that effect.
(b)If an infill project would result in significant effects that are specific to the project or the project site, or if the significant effects of the infill project were not addressed in the prior environmental impact report, or are more significant than the effects addressed in the prior environmental impact report, and if a mitigated negative declaration or a sustainable communities environmental assessment could not be otherwise adopted, an environmental impact report prepared for the project analyzing those effects shall be limited as follows:
…
Legislative history
Added by Stats. 2011, Ch. 469, Sec. 6. (SB 226) Effective January 1, 2012.