For purposes of this chapter, the following definitions apply:
(a)“Alternative project delivery method” means either Construction Manager/General Contractor method or design sequencing.
(b)“Construction Manager/General Contractor method” or “CMGC” means a project delivery method using a best value procurement process in which a construction manager is procured to provide preconstruction services during the design phase of the project and construction services during the construction phase of the project. The execution of the design and the construction of the project may be in sequential phases or concurrent phases.

Legislative history

Added by Stats. 2012, Ch. 767, Sec. 1. (SB 1549) Effective January 1, 2013.

Source: California Public Contract Code § 6951 from the California Legislative Information (public record). DecisionDepot is for informational use only and is not legal advice — verify against the official source before relying on this text.