California Public Contract Code
§ 10853
PCC § 10853 Effective Jan 1, 1993Div. 2 · Part 2 · Ch. 2.5 · Art. 8
Statute text
View on leginfo.ca.gov(a)If the trustees fail to make a progress payment on a contract within 39 days after receipt of an undisputed and properly submitted payment request from a contractor on a construction contract, the trustees shall pay interest to the contractor equivalent to the legal rate set forth in subdivision (a) of Section 685.010 of the Code of Civil Procedure. If the payment is not made within 39 days of receipt of the contractor’s request, and the Controller has processed the payment within 14 days of the receipt of the request, the trustees shall pay interest to the contractor equivalent to the legal rate as provided in subdivision (a) of Section 685.010 of the Code of Civil Procedure. If the payment is not made within 39 days of receipt of the contractor’s request, and the trustees have processed the payment within 25 days after the receipt of the request, the Controller shall pay interest equivalent to the legal rate as provided in subdivision (a) of Section 685.010 of the Code of Civil Procedure.
(b)Upon receipt of a payment request, the trustees shall act in accordance with the following:
(1)Each payment request shall be reviewed by the trustees as soon as practicable after receipt for the purpose of determining that the payment request is a proper payment request.
…
Legislative history
Added by Stats. 1992, Ch. 799, Sec. 1. Effective January 1, 1993.