Contract for Water-power—Construction.—A contract for the use of water as a motive power for a mill gives the mill no right to use such water for any other purpose.
Contract for Water-power—Damages for Breach.—Under a contract for the use of water as a motive power the mill owner is not damaged by a failure to deliver the amount of water called for, when an amount equal to the full capacity of plaintiff’s mill wheel is delivered.
Judgment—Pleading in Bar During Time for Appeal.—A judgment cannot be pleaded in bar during the time for appeal therefrom and while a motion for a new trial is pending.
GAROUTTE, J. This appeal is taken from the judgment and order denying a motion for a new trial. Upon the rendition of the judgment the trial court filed the following opinion regarding the questions involved in the litigation. It is lucid and convincing, and we are satisfied with the views there expressed:
“The pleadings in this case are quite voluminous, but the relief sought and prayed for may be divided into three heads: First. That a certain contract of writing, entered into by M. J. Church, the Fresno Canal and Irrigation Company, and the Fresno Milling Company, dated April 22, 1886, be canceled, and that the defendant, the canal company, be enjoined from using the same or asserting any rights thereunder. Second. That the defendant, the canal company, be required to furnish a deed in fee simple to the plaintiff to eighty-three and one-third cubic feet of water passing a given point per second. Third. That the defendant be required to pay said plaintiff damages for said canal company’s failure and neglect to furnish certain water agreed to be furnished to plaintiff, or the value of the rents and profits of certain water alleged to have been used by defendant, which plaintiff alleges rightfully belong to the plaintiff, the milling company. There are other questions, but they are corollaries of the foregoing propositions, and stand or fall with them.
“On the tenth day of September, 1885, a certain contract of writing was entered into between M. J. Church, the Fresno Canal and Irrigation Company, and one Joseph G. Deming. Under this contract said Church agreed to sell said Deming lots 28, 29, 30, 31 and 32, block A, of the town of Fresno, on which were then situated what were commonly known as the ‘ Champion Mills, ’ together with said mills and other improvements thereon, and the water-power to the amount of eighty-three and one-third cubic feet of water per second for running said mill, with all the privileges and appurtenances thereunto belonging or appertaining, for which said Deming agreed to pay the sum of $20,500—$10,000 in cash, and $10,500 thereof as soon as the canal used to convey water to said mill for motive power should be so enlarged and improved as to deliver to said mill for such motive power the amount of eighty-three and one-third cubic feet of water per second. The party of the second part, the Fresno Canal and Irrigation Company, [594]agreed to begin at once upon said canal to increase its capacity, as aforesaid, and to enlarge and improve the said canal so that it should deliver at the said mill, for its motive power, not less than eighty-three and one-third cubic feet of water per second; said work to be completed within ninety days. Said Church and the canal company further agreed that when said second installment of the purchase price of said property, to wit, $10,500, should be paid, that they would make, execute, and deliver to said Deming, as the grantee, a good and sufficient deed of grant of said property, which should convey to him a perfect title in fee simple, absolute, free and clear of all encumbrances, of said lots, with said mill and improvements thereon situated, together with all the privileges and appurtenances thereunto belonging, with a water right of eighty-three and one-third cubic feet of water per second for said mill during the existence of said corporation. The canal company further agreed that upon the payment of said sum it would furnish to said Deming, during the period of its existence, for the running of said mill, an amount of water equal to eighty-three and one-third cubic feet per second, providing that it should have the privilege of shutting off the water in said ditch during such times as should be necessary for the repairing of the same etc., and should not be held responsible for lack of water caused by drought, insufficient water in King’s river, hostile diversion, temporary damage by flood, etc., but that it should at all times use due diligence in restoring and maintaining the flow of water in said canal. It was also agreed that said Deming should have the right to turn in enough additional water to make up said amount into the mill canal, at any waste-way or bulkhead between the mill and the northwest corner of section 36, township 13 south, range 20 east, in case of any deficiency in said agreed supply, or that he might turn off any excess, if necessary. The canal company further agreed that it would enlarge the capacity of the ditch below the mill, so as to take away the water as fast as it should be necessary to prevent its impeding the running of the mill. This clause is also in said contract: ‘It is also understood and agreed by and between the respective parties hereto that the above grant to the party of the third part ['being said Deming]- of the water right of eighty-three and one-third cubic feet of water per second as a motive power for
More from California Supreme Court
- People v. Wende (1979)
- People v. Watson (1956)
- People v. Superior Court (Romero) (1996)
- People v. Kelly (2006)
- Auto Equity Sales, Inc. v. Superior Court (1962)
- Aguilar v. Atlantic Richfield Co. (2001)
- People v. Lewis (2021)
- In Re Estrada (1965)
- Denham v. Superior Court (1970)
- People v. Marsden (1970)