Perry v. Brainard
Before: Ross
Synopsis
Mechanics’ Liens—Time for Filing.—A mechanics’ lien is not acquired upon a building by a subcontractor who has furnished materials to be used thereon, by filing his claim prior to the completion of the building: Code Civ. Proc., see. 1187.1
ROSS, J. Defendant Brainard contracted to construct a certain dwelling-house for defendant Beaudry for a certain sum of money, and the plaintiffs contracted with Brainard to furnish certain material for the house. The court below found that the lien which was sought to be enforced by the action was filed prior to the completion of the building, and was therefore prematurely filed. The statute reads: “Every original contractor, within sixty days after the completion of his contract, and every person save the original contractor, claiming the benefit of this chapter, must, within thirty days after the completion of any building, improvement, or structure, or after the completion of the alteration or repair thereof, or the performance of any labor in a mining claim, file for record, ’ ’ etc.: Code Civ. Proc., see. 1187.
[592]It will be seen that the time prescribed by the statute for the filing of the plaintiffs’ claim was “within thirty days after the completion of the building.’’ Under a similar statute the supreme court of Kansas lately held in two cases (Davis v. Bullard, 32 Kan. 234, 4 Pac. 75, and Seaton v. Chamberlain, 32 Kan. 239, 4 Pac. 89) that a claim so filed was premature, and a lien based thereon could not be enforced. The reasoning of that court commends itself to our judgment, and is much the same as was used here in Dingley v. Greene, 54 Cal. 335. “No privity of contract,’’ said the court in Davis v. Bullard, “exists between the owner of the building and the subcontractor, but the subcontractor’s rights are based simply and solely upon his contract made with the contractor. The contractor, and not the.owner of the building, is the subcontractor’s debtor, and the subcontractor has no right to claim that the building has been completed until the contractor under whom he claims has such right. Under the contract between the owner and the contractor, the owner agrees to pay the contractor a certain sum for constructing the building, and this sum is a fund which may be held under the statutes for the payment, so far as it will go, of all the claims of all the various subcontractors, for work and materials furnished by them to the contractor, who is the principal and head of all; and all the parties entitled to payment or contribution out of this fund should be able to reach the fund and get their proportionate shares thereof at the same time or within the same period of time. Besides, one subcontractor ought not to be able to reach this fund and appropriate it to the extent of his claim before another subcontractor could reach it; for if the fund should not be sufficient to pay the claims of all the subcontractors, then each subcontractor should be paid only a proportionate share thereof. Now, the amount of all the claims of all subcontractors can be ascertained only after all the work and materials have been furnished, and after the building has been completed, so far as the contractor is required to complete the same; for the whole of the work may in fact be done by subcontractors only, or the last item of work performed or materials furnished may be performed or furnished by a subcontractor. The building in such a case would be completed by a subcontractor; and the subcontractor completing the build
More from California Supreme Court
- People v. Wende (1979)
- People v. Watson (1956)
- People v. Superior Court (Romero) (1996)
- People v. Kelly (2006)
- Auto Equity Sales, Inc. v. Superior Court (1962)
- Aguilar v. Atlantic Richfield Co. (2001)
- People v. Lewis (2021)
- In Re Estrada (1965)
- Denham v. Superior Court (1970)
- People v. Marsden (1970)