Santa Monica Lumber & Mill Co. v. Hege
Before: Harrison
Synopsis
Mechanic's Lien—Contract fob Materials—Record, when not Required. Where a lessee, for the purpose of constructing certain additions to the premises leased, purchased materials therefor of less value than one thousand dollars, the provisions of the code relating to a written contract and filing the same for record have no application.
Id.—Lien fob Materials—Time for Notice—Completion of Building— Premature Filing.—The lessee having caused the improvements to be constructed for himself, the party furnishing the materials was not an original contractor, and must file a notice of lien within thirty days after the completion of the building; and unless the building • was completed before the notice of lien was filed, the filing was premature, and conferred no right to enforce the lien.
Id.—Finding—Completion before Notice—Date Immaterial—Conflict of Evidence.—A finding that the building was completed at a particular date, which was prior to the notice of lien, is not material so far as the date is concerned; and though there may be no evidence as-to the date of completion, it is sufficient that there is evidence tending to show that the building was completed before the notice ot lien was filed, and the finding cannot be disturbed on account of conflicting evidence upon that issue.
Id.—Test of Completion—Absence of Plans—Presumption—Matters not Included—Trivial Imperfection.—In the absence of any plans of the building, or means of test by which it could be determined when the building was completed, its completion must be determined by the court from all the circumstances of the case shown by the evidence; and where it appeared that no sidewalk was ever constructed, that the building was never painted, and that no eave-troughs or waterclosets were ever constructed, it is to be presumed, in the absence of evidence to the contrary, that the original plans of the building, did not include any of these matters and the court might properly so find; and the failure to make the ridge of the roof tight, and to putty the glass on the outside, is merely a defective performance of the work rather than a failure of completion, and was properly disregarded as a “trivial imperfection.”
Id.—Construction by Lessee—Liability of Owner—Absence of Notice.— Where improvements to the building were constructed by the lessee with the previous knowledge and permission of the owner, his failure to give the notice required by section 1192 of the Code of Civil Procedure rendered his interest in the land subject to the lien of one furnishing materials for the improvements; and it is immaterial whether they were constructed in the particular form, or at the particular place which was authorized by the owner.
Id.—Void Notice of Lien—Incorrect Statement as to Contract Price— Variance.—The right to enforce a mechanic’s Ken depends upon a compliance with the statute; and not only must the notice of lien contain the statements required by section 1187 of the Code of Civil Procedure, but the statements thus made must be in accordance with the facts, and if they are not correctly stated the right to a lien is lost; and though proof that the contract was for the “regular market price” is not a substantial variance from an allegation that the contract was for what the materials were reasonably worth; yet where the notice incorrectly stated the amount of the balance due as the amount of the contract price of the lumber, and that no part thereof had been paid, proof that the contract was for a considerably larger price and that payments had been made thereon, shows a fatal variance in the terms of the contract from that stated in the notice, and renders the notice of lien defective and void.
HARRISON, J. Action for the foreclosure of a mechanic’s lien. In May, 1894, the defendant Hege being the owner of a' lot of land in the town of Santa Monica, on which there was a dwelling-house, verbally leased the same to his codefendant, Naumann. Shortly after Naumann had entered into possession he obtained permission from Hege to construct certain additions to the building, and for that purpose purchased certain materials from the plaintiff which were used in their construction. August 11, 1894, the plaintiff filed with.the county recorder its claim of lien therefor upon the land and buildings, and afterward brought the present action for its enforcement. Naumann suffered default, and judgment was rendered against him for the amount [378]claimed by the plaintiff, declaring said amount to be a lien upon the land, and directing its sale. From this judgment Hege has appealed.
As the amount of the materials purchased from the plaintiff was less than $1,000 in value, the provisions of the code relating to a written contract and filing the same for record have no application. Haumann caused the improvements to be constructed for himself, and the plaintiff, not being an “original contractor” (Sparks v. Butte County Gravel Co., 55 Cal. 389), was required to file its notice of lien within thirty days after the completion of the building. Unless the building was completed before the notice of lien was filed, the filing was premature and conferred no right to enforce the lien. (Roylance v. San Luis Hotel Co., 74 Cal. 275; Schwartz v. Knight, 74 Cal. 432; Willamette etc. Co. v. Los Angeles College Co., 94 Cal. 229.)
The court finds that the building was completed July 23, 1894, but this finding is attacked as not supported by the evidence. There is no evidence in the record fixing this day as the date on which the building was completed, "but, as it was sufficient for the plaintiff to show that the building was completed before its notice of hen was filed, any finding of the particular day was not essential and may be disregarded. There was a conflict of evidence upon this issue, and we cannot say that the finding of the court in favor of the plaintiff was erroneous. Emerson, who worked as a carpenter on the building, testified that he finished work in the latter part of June, and that the buildings were completed “shortly after,” and that at the time of the trial the building was in the same condition as then. Naumann testified that the building was not finished on August 11th, and, as items of its incompleteness, mentioned, among others, that it had not been painted and that a sidewalk had not been constructed. It was not shown that any plans of the building were «ver prepared, or that there was any test by which it could be -determined when it was completed, and, in the absence of such test, its completion would be determined by the court from all the circumstances shown by the evidence. Presumptively, a sidewalk would not be a part of a building; and, as it was shown that the building had never been painted, the court was authorized, in the absence of any evidence on the subject, to find that painting
More from California Supreme Court
- People v. Wende (1979)
- People v. Watson (1956)
- People v. Superior Court (Romero) (1996)
- People v. Kelly (2006)
- Auto Equity Sales, Inc. v. Superior Court (1962)
- Aguilar v. Atlantic Richfield Co. (2001)
- People v. Lewis (2021)
- In Re Estrada (1965)
- Denham v. Superior Court (1970)
- People v. Marsden (1970)