Dore v. Sellers
Before: Rhodes
Synopsis
Lien of Contractor on Building.—The statute gives one who has entered into a contract in writing to construct a building a lien on the same as security for the payment of the money becoming due to him according to the terms of the contract, but this lien cannot be enforced for an amount exceeding the sum to become due the contractor.
Contractor has no Lien except for Money to become Due.—If a contractor engages to construct a building in consideration—in whole or in part—of a debt then due from him to the employer, or of a sum paid him by the employer upon the execution of the contract, that portion of the contract price represented by the debt or the advance payment cannot become a lien upon the building.
Lien of ÍImployíes of Contractor.—The employés of the contractor have no lien on the building as principals, and cannot acquire a lien on the building independent of the one existing on the original contract, which they may enforce to the amount due them, so that the same does not exceed the sum for which the contractor has a lien.
Lien of Employes of Sub-Contractor.—If the contractor has paid the sub-contractor according to the terms of his contract with him, and has not made premature payment, the employés of the sub-contractor are not entitled to demand anything from the contractor or employer.
Same.—The employés of the sub-contractor cannot intercept any money due from the employer to the contractor, nor can they enforce the lien of the contractor for any of the same, beyond what is due from the contractor to the sub-contractor at the time.
By the Court, Rhodes, J. This action is brought under the Mechanics’ Lien Act of 1862. Sellers and Goldstein, being the owners of a certain lot in San Francisco, contracted in writing with Griblin for the construction of two houses for a price named, payable in instalments. Griblin contracted in writing with Zurn and Hannigan to do the carpenter work on the buildings and furnish the materials for the work. On the 12th of January, 1863, the sub-contractors gave notice to the contractor and the architect, that they could not complete their contract, and they then abandoned the work. The contractor, up to that time, had paid to the sub-contractors all that was due them for work done and materials furnished by them, and it is not alleged and does not appear that a further sum was to become due to them, for work done or materials furnished before that time. On the 15th of January, 1863, the plaintiff served upon the owners of the premises and the contractor, a notice of his claim as a material man, for lumber, etc., furnished to the subcontractors for the erection of the houses, the bill for which was on the 13th of January, 1863, certified by the sub-contractors to be correct. Upon the sub-contractors abandoning their contract, the contractor (Griblin) proceeded to complete [592]the buildings, including that portion of the work uncompleted under the sub-contract; and at the time they abandoned their contract five thousand eight hundred and sixty dollars, as appears by the stipulation of the parties, “ remained to be earned and paid upon the original contract as between the original parties (said Gfiblin, Goldstein and Sellers,) in two instalments—one of fifteen hundred dollars, and the last of four thousand three hundred and sixty dollars—to be paid on completion of the job. Fully completed March 20, 1863.” The plaintiff sued to enforce his lien upon the lot as a material man, and he makes as defendants the owners of the lot and the sub-contractors.
The intervenor’s position is similar in all respects to that of the plaintiff. The defendants had judgment in the Court below.
’ The appellants state the question involved in the case as follows: “ Can the material man and laborer go upon the house, superstructure, etc., directly to the extent of the contract price due, or are they subject to all the conditions which may be created by the account between the contractor and his sub-contractor?” and in solving this question they lay down the proposition that, under the Mechanics’ Lien Law, the material man and laborer are entitled to a lien upon the premises, as principals, subject to the limitation only, that the amount of such lien shall not exceed the price agreed to be paid by the owner of the real estate to the original contractor for the whole work. If this proposition can be maintained, the question must be answered in the affirmative.
More from California Supreme Court
- People v. Wende (1979)
- People v. Watson (1956)
- People v. Superior Court (Romero) (1996)
- People v. Kelly (2006)
- Auto Equity Sales, Inc. v. Superior Court (1962)
- Aguilar v. Atlantic Richfield Co. (2001)
- People v. Lewis (2021)
- In Re Estrada (1965)
- Denham v. Superior Court (1970)
- People v. Marsden (1970)