Miltimore v. Nofziger Bros. Lumber Co.
Before: Shaw
Synopsis
The facts are stated in the opinion of the court.
Opinion
THE COURT.
The plaintiff was the owner of a lot upon which she had caused a building to be erected. When it was completed there remained unpaid a portion of the contract price which she had agreed to pay for the erection of the building. The other parties to the several appeals here under consideration, except the original contractor, are persons
[791]
claiming liens on the property for labor done or materials furnished in the building. The unpaid balance was not sufficient to pay all the liens, and the owner being unable to determine with certainty the amount or priority of the respective liens, and there being some dispute among the lien claimants concerning their respective claims and rights of priority, she began the main action, bringing the money unpaid into court, summoning all parties claiming an interest therein to appear and interplead as to their respective rights to the fund, and asking to be relieved from further responsibility in the matter.
Some of the parties began independent actions to foreclose their liens and some appeared in the main action and filed cross-complaints therein for such foreclosure. The actions were, however, all consolidated in the lower court and tried together. Judgment was given in favor of the owner as prayed for in her complaint. The rights of the several lien claimants to the fund were declared by the judgment in accordance with their rank as provided by section 1194 of the Code of Civil Procedure, the laborers being given the first right, the materialmen the second right, the residue, if any, being given to the subcontractors. There were among the several claimants representatives of each of these classes.
The subcontractors contend that all the claimants are entitled to share alike in the fund, without preference of one over the other, this claim being founded on the proposition that section 1194 aforesaid, so far as it declares that one class of lienholders shall have priority over another, is unconstitutional. The materialmen contend that, at all events, it is invalid so far as it gives the laborers preference to the persons who furnish materials for the building. It is stipulated that these comprise the only questions to be determined upon the respective appeals, there being separate appeals on behalf of the materialmen and subcontractors, respectively.
More from California Supreme Court
- People v. Wende (1979)
- People v. Watson (1956)
- People v. Superior Court (Romero) (1996)
- People v. Kelly (2006)
- Auto Equity Sales, Inc. v. Superior Court (1962)
- Aguilar v. Atlantic Richfield Co. (2001)
- People v. Lewis (2021)
- In Re Estrada (1965)
- Denham v. Superior Court (1970)
- People v. Marsden (1970)