Eminent Domain—Dismissal of Proceeding After Verdict and Before Degree—Excessive Verdict—Abandonment.—The plaintiff in an action of eminent domain, after trial and verdict fixing the amount of compensation and damages, may, within thirty days thereafter and before any further proceedings are had, move the court to dismiss the action upon the statement “that the damages and values fixed by the jury were excessive, and a dismissal of the ease was an abandonment by the plaintiff of its claim for the property.” He is entitled to abandon the claim to the property and ask a dismissal before the expiration of thirty days from the entry of judgment.
Id.—Discretion of Court—Distinction Between Conditional Dismissal and Absolute Dismissal With Judgment for Costs.—• Assuming, without deciding, that such right of dismissal is within the discretion of the court only, subject to review in case of abuse, and that in its exercise the court may impose such terms as in its judgment may be proper as a condition of its exercise, yet there is a marked distinction between a conditional dismissal, the effect of which is to order a dismissal upon the performance of certain conditions, and an absolute dismissal, such as appears in this ease, where a judgment is entered for costs and expenses of suit.
Id.—Improper Judgment for Expenses Beyond Costs—Attorneys’ Eees—Pees of Engineer for Work and Maps.—There is no authority in the statute authorizing a court to render a judgment for attorneys’ fees, and the fees of an engineer for work and maps, in excess of costs, in connection with an unconditional order dismissing a proceeding in condemnation, whatever may be its authority in imposing payment thereof, as a condition precedent to dismissal. Id.—Statement on Motion to Dismiss Sufficient Evidence of Abandonment.—The statement by plaintiff in open court, in connection with his motion to dismiss, to the effect that if such motion was granted it would abandon all claim to the property, amounted to such an abandonment as would warrant the order of dismissal with a judgment for costs only.
Opinion — Allen
ALLEN, P. J.
The action was one instituted by plaintiff in the exercise of the right of eminent domain. The cause proceeded to a trial before a jury and a verdict fixing the amount of compensation and damages. Within thirty days thereafter, and before any further proceedings were had, plaintiff moved the court to dismiss said action upon the grounds “that the damages and values fixed by the jury were excessive, and a dismissal of the case was an abandonment by the plaintiff of its claim for the property.” Defendant objected to such dismissal and moved for a judgment to be entered upon the verdict, but in the event the same should be denied, asked that the dismissal be ordered upon terms and conditions which involved the payment of costs and defendant’s reasonable expenses in preparing for and defending the action, including $29 for surveying and engineering work and maps thereof and $1,000 attorneys’ fees, and that plaintiff be precluded from hereafter commencing another action to condemn the same strip of land here sought to be condemned, or any strip of land in that vicinity across the land of said defendant. These motions were heard and submitted. The court overruled defendant’s objection to a dismissal, and “the court now orders said action to be dismissed on the terms and conditions hereinafter mentioned. Wherefore, by reason of the law and the premises, it is considered, adjudged and decreed as follows': that defendant Reis Estate Company do have and recover from said plaintiff its costs and disbursements herein, taxed at $225; also its necessary and reasonable expenses in preparing for and defending this action, namely, $29 for surveying and engineering work and maps thereof, and $750 attorney fees; that this action be and the same is hereby dismissed.” Plaintiff appeals from that part of the judgment by which it was and is adjudged that defendant do have and recover from plaintiff its necessary and reasonable expenses in preparing for and defending this action;
[218]
namely, $29 for surveying and engineering work and maps and $750 attorney’s fees.
It is insisted by appellant that having abandoned its claim to the property within thirty days succeeding the trial, it was entitled to have its action dismissed upon payment of the costs, and that the court was without authority to include in such judgment any penalty or amount in excess of such costs. Upon the other hand, it is respondent’s contention that the dismissal was a conditional one, to be made and entered upon payment of the sums ordered by the court, and that such conditional dismissal was within the discretion of the court, and that no abuse of discretion appearing, it must be assumed upon this appeal that the same was properly exercised. We think it unnecessary to determine the character of right with reference to dismissal which a plaintiff may possess in proceedings of this character after verdict and before final decree of condemnation. That he is entitled to abandon the claim to the property and ask a dismissal before the expiration of thirty days from the entry of the judgment has been determined in
More from California Court of Appeal
- People v. Hill (1998)
- In Re Autumn H. (1994)
- Nwosu v. Uba (2004)
- In Re Casey D. (1999)
- Santisas v. Goodin (1998)
- Cahill v. San Diego Gas & Electric Co. (2011)
- People v. Rivera (2015)
- People v. Barnett (1998)
- People v. Serrano (2012)
- Benach v. County of Los Angeles (2007)