Western Oil & Refining Co. v. Sullivan
Before: Thompson
THOMPSON (IRA F.), J.
This is an appeal from a judgment rendered in favor of the plaintiff corporation in a claim and delivery action. The facts essential to an understanding of the case are briefly as follows: On November 27, 1928, the appellant owned certain land, together
[320]
with all the oil and eighty per cent of natural gas that might be produced therefrom. Being desirous of drilling for the oil and gas he entered into a contract with respondent on that date whereby respondent agreed, in consideration of the contemporaneous execution of a gas contract in its favor, to place at the disposal of appellant for a period of seven months two boilers to be used in the drilling of a well. There was included in the contract a provision that when the well should be placed on production respondent should retain sufficient of the royalty gasoline belonging to appellant to pay for the boilers in the sum of $4,850, plus interest at seven per cent from the date of the agreement. Respondent furnished the equipment as agreed, but the seven months passed without any funds being raised or made available by the appellant for the work of drilling. On June 22, 1929, upon the statement of appellant’s representative to a Mr. Bsselstyn, acting for respondent, that appellant expected some money from the east, the latter said to forget about the boilers “until some higher officer would mention it to him, and he figured that it could be fixed to our satisfaction”. Again, about the middle of July of the same year a Mr. Taylor told the same witness, the manager for appellant: “that the boilers would be left there until the time that the money came, and that I would see them—at that time they would take up the proposition of extending the time by contract”. Finally, on September 25, 1929, the hope of securing funds which was springing in appellant’s breast had completely waned so far as respondent was concerned, and it demanded the return of the boilers. Upon refusal of the appellant to deliver them up this action was brought resulting in a judgment for their recovery together with interest upon their value from the date of the contract at seven per cent per annum.
There are two reasons advanced why we should reverse the judgment, the first being that the right of possession of the machinery was in appellant by virtue of the oral agreement and the other that the court was not authorized either by the evidence or the pleadings to award plaintiff a judgment for the interest.
More from California Court of Appeal
- People v. Hill (1998)
- In Re Autumn H. (1994)
- Nwosu v. Uba (2004)
- In Re Casey D. (1999)
- Santisas v. Goodin (1998)
- Cahill v. San Diego Gas & Electric Co. (2011)
- People v. Rivera (2015)
- People v. Barnett (1998)
- People v. Serrano (2012)
- Benach v. County of Los Angeles (2007)