Alcatraz Etc. Assn. v. U.S. F. Etc. Co.
Before: HARRISON, P. J. —
The plaintiff entered into a contract with one L. U. Grant, October 19, 1899, for the construction by the latter of a building upon its land at the agreed price of $16,300, and at the same time the said Grant as principal and the defendant as surety executed to the plaintiff a bond of indemnity in the sum of $4,075, conditioned that Grant should faithfully perform the said contract and deliver the building to the plaintiff within the contract time for its completion, free from all liens, demands and claims, and should pay to the persons performing labor or furnishing materials for the construction of the building the value thereof. The contract provided that the building should be completed within *Page 340 one hundred and fifty working days from the date thereof, and that the payment of the contract price should be made in installments as the work progressed, in sums equal to seventy-five per cent of the value of the work done and materials furnished, as estimated on the first and fifteenth days of each month, and the balance, to wit, twenty-five per cent of the contract price of $16,300 ($4,075) thirty-five days after the completion and acceptance of the work. After the execution and recording of the contract the plaintiff and Grant made certain alterations and changes therein, by which the cost of the building was increased in the sum of $315, and agreed that the said additional cost should be paid at the same times and in the same manner as payments under the original contract. During the progress of the work payments were made to Grant upon certificates of the architect on account of installments due on the contract, amounting to $12,138.85. Before the building was completed Grant abandoned the contract, and the plaintiff completed the construction of the building and expended therefor $641.23. After its completion certain parties, who had furnished materials and performed labor for Grant in its construction, filed claims of lien therefor, amounting to about $7,500, and subsequently brought actions in the superior court for their enforcement. These actions were, by an order of court, consolidated, and the plaintiff filed its answer thereto, alleging that the building was not subject to liens exceeding in the aggregate $3,834.92, and offering to deposit that sum in court for their satisfaction. Upon the trial of the cause the court found that that was the amount due from the plaintiff to Grant upon the contract at the commencement of the action; and upon its order the sum was deposited in court for the said claimants, and the court thereupon rendered its judgment that the said liens were thereby fully satisfied. In this litigation the plaintiff employed certain attorneys, for whose services he paid $500, and incurred certain costs, amounting to $27. The present action is brought to recover these amounts from the defendant. A demurrer to the complaint was sustained, and from the judgment entered thereon the plaintiff has appealed. *Page 341
More from California Court of Appeal
- People v. Hill (1998)
- In Re Autumn H. (1994)
- Nwosu v. Uba (2004)
- In Re Casey D. (1999)
- Santisas v. Goodin (1998)
- Cahill v. San Diego Gas & Electric Co. (2011)
- People v. Rivera (2015)
- People v. Barnett (1998)
- People v. Serrano (2012)
- Benach v. County of Los Angeles (2007)