Neill v. Klobas
Before: Stone
STONE, J. pro tem.
*
Plaintiffs and cross-defendants, hereinafter referred to as plaintiffs, the owners of real prop
[325]
erty in Richmond, entered into a written contract with defendants and cross-complainants, hereinafter referred to as defendants, for the construction of a “multiplex” of 11 units with carports. The contract price was $54,880, payable in five installments of $8,476 each, and a note and trust deed for $12,500 payable on or before completion. Plaintiffs arranged to finance construction through the Mechanics Bank of Richmond which placed $33,000 in plaintiffs’ loan account, plaintiffs adding $9,618.95 in cash. The remainder of the contract price, which was evidenced by the $12,500 note and trust deed, was to be obtained by plaintiffs’ selling their home in Berkeley. The bank, however, required a bond guaranteeing that construction would be completed before releasing any of the building account funds. This required an immediate sale of the Berkeley property and a deposit of the proceeds in the building account in lieu of the note and deed of trust. Plaintiffs were unable to sell the property and obtain the bond. Both parties repeatedly tried to secure the bond, without success. Defendants commenced excavating but shortly thereafter plaintiffs notified them that the Berkeley property had not sold; that the listing had expired; and that they were not going to renew the listing. This meant that no completion bond could be obtained, so defendants stopped work.
Plaintiffs sued for rescission of the contract and to quiet title against the note and deed of trust. Defendants cross-complained for damages for breach of contract. It was disclosed during trial that plaintiffs had negotiated with another contractor for a smaller and different type of “multiplex” costing less money. The negotiations with the other contractor occurred before plaintiffs notified defendants that they were not going ahead with the contract, but the building was not constructed until after rescission.
The court made separate findings of fact and conclusions of law for the complaint and for the cross-complaint. Both present essentially the same issue, breach of contract, and the findings and conclusions of law as to each are predicated upon the same evidence. Yet, the conclusions of law as to the issues raised by the complaint hold that there was no breach of contract, but a mutual abandonment, while the conclusions of law as to the same issues raised by the cross-complaint hold that the plaintiffs breached the contract. This conflict between the conclusions of law on the complaint and cross-complaint based upon the same evidence is basic and
More from California Court of Appeal
- People v. Hill (1998)
- In Re Autumn H. (1994)
- Nwosu v. Uba (2004)
- In Re Casey D. (1999)
- Santisas v. Goodin (1998)
- Cahill v. San Diego Gas & Electric Co. (2011)
- People v. Rivera (2015)
- People v. Barnett (1998)
- People v. Serrano (2012)
- Benach v. County of Los Angeles (2007)