Bodmer v. Turnage
Before: Barnard
BARNARD, P. J.
This is an appeal from a judgment awarding the plaintiff payment for his services as an architect.
In July, 1948, the defendant purchased certain lots in Borrego Valley, a desert resort development. He agreed to pay $39,000 for the lots, and to spend in improving the property $100,000 the first year, $50,000 the second year, and $50,000 the third year. On August 10, 1948, he entered into a written contract with the plaintiff. After reciting that the defendant intended to erect a resort at Borrego Springs consisting approximately of 30 housing units, a clubhouse, a café, a cocktail lounge, a swimming pool and roads and appurtenances, the contract provided that the plaintiff was to
[476]
prepare preliminary studies, working drawings and specifications, and furnish other specified services “for the above named work”; that the defendant would pay for these services 6 per cent of the cost of the work, one-fifth being payable upon completion of the preliminary studies and the balance as the work progressed; and that if any work designed by the plaintiff was abandoned or suspended he was to be paid for his services in that connection. During the next few months the plaintiff prepared and presented a total of five sets of preliminary studies and plans. In each instance except the last, the defendant suggested changes he desired and new plans were prepared accordingly. The fifth plan was approved by the defendant on or about January 7, 1949, and the plaintiff was told to proceed with the preparation of working drawings and specifications as rapidly as possible. Late in March, 1949, the plaintiff was told by a contractor on the job that the work was to be abandoned, and still later he was notified to this effect by the defendant.
The complaint in this action was in two counts, and sought recovery of $3,192 as the agreed price, and also as the reasonable value, of the services in connection with the preliminary studies and plans, and the further sum of $1,075.20 as the reasonable value of the work thereafter done in preparing working plans and specifications. The court found in all respects in favor of the plaintiff finding, among other things, that the contract above referred to had been executed; that the plaintiff had completed his work in connection with the preliminary studies and plans; that these plans were accepted by the defendant on or about January 7, 1949; that with the full knowledge and approval of the defendant the plaintiff had been engaged in the preparation of working drawings and specifications until notified that his services were no longer desired; and that the defendant had for personal reasons abandoned the project and indefinitely postponed the erection of such resort or any part thereof. It was further found that at the time the preliminary studies were completed the estimated cost of the work was1 $236,000; that the reasonable value of the services performed by plaintiff up to that time is $2,832; and that the reasonable value of the services performed thereafter is $1,075. Judgment was entered for $3,-907, and this appeal followed.
More from California Court of Appeal
- People v. Hill (1998)
- In Re Autumn H. (1994)
- Nwosu v. Uba (2004)
- In Re Casey D. (1999)
- Santisas v. Goodin (1998)
- Cahill v. San Diego Gas & Electric Co. (2011)
- People v. Rivera (2015)
- People v. Barnett (1998)
- People v. Serrano (2012)
- Benach v. County of Los Angeles (2007)